E.ON develops MMP3
E.ON Benelux is already operating a coal power plant with two units (1.040 MW combined) on the Maasvlakte and the construction of a third is currently underway. The Maasvlakte Power Plant 3 (MMP3) has a capacity of circa 1070 MW.
MMP3 is an ultramodern coal power plant which uses powdered coal to generate steam with exceptionally high steam conditions (285 bar, 600 to 620 °C). The steam is converted into electricity with the use of a turbine and a generator. This means that the unit will supply circa 7% of the national electricity consumption.
This puts MMP3 in the category of the largest coal fired units built in the world. The construction costs amount to approximately 1,2 billion euro. The plant should be operational by December 2012.
As commissioned by E.ON Benelux, Burdock supports this project in the areas of contract management (civil), cost control and administrative support.
More news
- Burdock sponsors contract management conference 23-08-2010
- New office space in Amsterdam 16-08-2010
- Burdock in Abu Dhabi 16-08-2010
- Burdock opens office in Indonesia 16-08-2010
- Burdock Australia 16-08-2010
- Burdock opens new office in Eemshaven 16-08-2010
- Burdock branches out into Contract Management 16-08-2010
- HDS-6 Shell Pernis 16-02-2010
- Excellent start for Burdock Energy Solutions 16-02-2010
- Saudi Aramco 16-02-2010
- E.ON develops MMP3 16-02-2010
- ENI Congo 16-02-2010
- Essent CCGT Power Plant 16-02-2010
- Burdock branches out into offshore 16-02-2010
- Scaldiahaven Vlissingen 16-02-2010
- International succes 22-10-2009
- Burdock Oil & Gas International 22-10-2009